Ground Up Construction Financing: 7 Smart Questions

Ground up construction financing in Florida, from lot to certificate of occupancy: the 7 questions that decide your loan, your cash and your lien exposure.

Ground Up Construction Financing at a Glance: Answer These 7 Questions First

Ground up construction financing funds land, materials and labor through a draw schedule. Lenders size it on the lower of two limits: a percentage of your total project cost and a percentage of the finished home’s value. Most private lenders land between 75% and 90% of cost. On value they land between 65% and 75%. You fund the rest.

That gap decides whether you can build the deal at all. Seven questions set it, and all seven have answers before you buy the lot.

A build goes wrong in ways a flip does not. The collateral does not exist yet. Your money goes out before each draw comes back. In Florida, a subcontractor you never hired can file a lien against your property. This guide covers all of it, with a worked Tampa example from lot purchase to certificate of occupancy.

Requity Lending provides ground up construction financing for real estate investors and builders, and Florida is our home market. We also make the fix and flip loans and DSCR loans that many builders use before and after a build. This article is general information, not financial, legal or tax advice.

What Is a Ground Up Construction Loan?

A ground up construction loan is short term financing that funds a new build on vacant land, releasing construction funds in stages as the work gets done. It covers the lot, the hard construction costs and most soft costs. It runs interest only for 12 to 24 months, until you sell the finished house or move it onto long term financing.

Three things separate it from a rehab loan:

  • The collateral does not exist yet. The lender underwrites your plans, your budget and your builder, not a standing house.
  • Money moves backward. You or your builder pay for completed work, then the lender inspects and reimburses it.
  • The timeline is longer and less certain. Permits, inspections and weather all sit between you and the next draw.

Builders use ground up construction financing for spec homes, infill lots, teardowns and small rental developments. Most projects are single family homes, though many lenders also fund 2 to 4 unit builds. You will see the term written both ways, with and without the hyphen, and it means the same thing.

Ground up construction financing sized on the lower of loan-to-cost and as-completed value

The 7 Questions to Answer Before You Build

1. Is the lot actually build-ready?

A lot that looks buildable can still stop a loan. Before you go under contract, confirm:

  • Zoning and use. The district has to allow what you plan to build, at the density you plan.
  • Utilities. Water, sewer or septic approval, power and, in rural parcels, a well. Running sewer 300 feet costs real money.
  • Access and survey. Legal access, recorded easements and a boundary survey that matches the plat.
  • Soil and grade. A soil test tells you whether the foundation you budgeted will work.
  • Flood zone and elevation. In a FEMA Special Flood Hazard Area, a finished floor has to sit at or above the required elevation, which changes your foundation cost.

Lenders call this entitlement risk, meaning the risk that approvals never come. The further along you are, the better your terms. A permitted lot is worth more than a raw one.

2. What is my total project cost, and what will the lender actually fund?

Total project cost is the lot plus hard costs plus soft costs. Write all three down before you ask for a quote:

Cost type What it includes
Land Purchase price or appraised value if you already own it
Hard costs Site work, foundation, framing, roof, mechanical, electrical, plumbing, finishes, landscaping
Soft costs Construction plans, engineering, permits, impact fees, survey, builder’s risk insurance, utility connections

Lenders then apply two caps and lend the lower one:

Loan = the lower of (total project cost × maximum LTC) and (as-completed value × maximum LTARV)

Loan-to-cost (LTC) measures what you spend. Loan-to-after-repair-value (LTARV) measures what it will be worth. When cost is the binding limit, you fund the difference. When value is the binding limit, your margin is too thin and the deal probably needs a cheaper lot.

3. How much cash do I need at closing, and how much over the build?

Your cash is not one number. It arrives in three waves:

  • At closing: the part of the lot the loan does not fund, origination, Florida doc stamps and intangible tax, title, survey and legal.
  • During the build: the share of each draw the loan does not cover, plus everything you pay before the lender pays you back.
  • Carrying the project: interest, insurance, taxes and utilities until the house sells or refinances.

Ask every lender one question: do you fund draws in arrears? Almost all do. That means you pay the concrete sub before the money arrives, so your working capital, not the loan, carries the project between draws.

4. How does the draw schedule work, and can I float the gaps?

A draw schedule ties money to milestones, usually foundation, framing, dry-in, mechanical rough-in, drywall, finishes and completion. The draw process is the same each time: a request, an inspection, and sometimes lien releases from everyone who worked on that phase. Construction draws are reimbursements, not advances.

Two numbers matter more than the schedule itself: how long an inspection takes to clear, and how long funding takes after that. A lender that funds in 48 hours and one that funds in two weeks produce very different cash flow on the same build.

An interest reserve can hold back part of the loan to cover interest payments during construction, since the property earns nothing until it sells. It is useful, but it is still your money: a reserve raises the loan and the total interest you pay.

5. Do my builder and I qualify?

The lender underwrites your builder as closely as it underwrites you. Expect to provide:

  • A current Florida contractor’s license and proof of general liability and workers’ compensation insurance
  • A signed, fixed-price contract or a detailed cost breakdown by trade
  • The builder’s recent comparable projects
  • A construction schedule tied to the draw milestones
  • Builder’s risk insurance, with the lender named on the policy

If you plan to act as your own general contractor, say so early. Florida limits who can pull permits as an owner-builder, and many lenders decline owner-builder projects outright.

You get underwritten too. Most construction lenders want a credit score in the mid-600s or higher, and the score moves your rate and your leverage. They also look at your liquidity, because a build needs cash on hand, and at any ground up construction loans you have finished before. Loan amounts on residential programs usually run from about $100,000 to several million, with single family homes the most common project type.

6. How do I protect myself from Florida’s construction lien law?

This is the question most out-of-state builders miss. Under Chapter 713 of the Florida Statutes, a subcontractor or supplier with no direct contract with you can still lien your property. They serve a Notice to Owner, generally within 45 days of first supplying labor or materials, and that preserves their lien rights.

The practical protection is paperwork, every single draw:

  • Record a Notice of Commencement before work starts, and post it at the job site.
  • Track every Notice to Owner you receive. Each one marks someone who can lien the property.
  • Collect conditional and final lien releases from the general contractor and every sub and supplier who sent a notice, matched to each payment.
  • Never pay a draw without the matching releases. Paying your general contractor in full does not stop an unpaid sub from liening you. That is exactly what the statute warns owners about.

Your lender and title company will require most of this anyway, because a lien jumps ahead of a careless lender’s mortgage. Treat it as your protection too, not just theirs.

7. What is my exit, and have I underwritten it?

Every construction loan ends in one of three ways. Decide which before you break ground:

  • Sell the finished house. Underwrite the sale price from closed comps of similar new construction, not from asking prices.
  • Refinance into a rental loan. A DSCR loan can take out the construction loan once the house is finished and leased. A bank would call that a construction to permanent loan; with a private lender it is two separate loans. Check that the rent supports the new payment before you build, the same way a BRRRR investor checks it.
  • Refinance into a longer bridge. The most expensive option, and the one you fall into when the first two are not ready.

A certificate of occupancy usually gates all three. Build your timeline to the CO, then add the weeks your exit lender needs to close.

Worked Example: A Tampa Spec Build

A sample 1,800 square foot spec home on an infill lot. All figures are examples, not a quote or an offer of credit. The lender terms below reflect what private construction lenders commonly offer, since terms vary by lender, builder experience and project.

The budget

Line Amount
Lot purchase $90,000
Hard construction costs $285,000
Soft costs (plans, permits, impact fees, survey, insurance) $35,000
Total project cost $410,000
As-completed appraised value $540,000

Sizing the loan

Limit Math Maximum loan
85% of total project cost 85% × $410,000 $348,500
70% of as-completed value 70% × $540,000 $378,000

Cost is the binding limit, so the loan comes in at $348,500. You fund the remaining $61,500, which is 15% of the project.

What you bring at closing

The loan funds 70% of the lot at closing and the rest through draws.

Item Amount
Lot equity ($90,000 less $63,000 advanced) $27,000
Origination (2%) $6,970
Florida doc stamps on the note and intangible tax $1,917
Title, survey, legal and recording (estimate) $6,000
Cash at closing $41,887

Another $34,500 of your equity goes in across the build, as your share of each draw.

Cash required for ground up construction financing on a $410,000 Florida build

Interest during the build

Interest runs at 10.75% on the drawn balance only. The balance climbs as draws go out, so the monthly payment climbs with it.

Month Drawn balance Interest
1 $63,000 $564
3 $126,444 $1,133
5 $189,889 $1,701
7 $253,333 $2,269
9 $316,778 $2,838
10 $348,500 $3,122
Total, 10 months $18,432

That total is what an interest reserve would need to cover.

Drawn balance and monthly interest across a ground up construction loan

The result

Item Amount
Total project cost $410,000
Loan costs and closing (origination, taxes, title) $14,887
Interest, 10 months $18,432
All-in cost $443,319
Sale price (as-completed value) $540,000
Selling costs (5% commission, deed doc stamps, closing) ($33,280)
Net profit $63,401

Net profit is 11.7% of the finished value. [VERIFY: Requity lending team insight on what margin a Florida spec build needs before we will finance it]

Stress test

Scenario Net profit
Base case $63,401
Build runs 3 months long $54,035
Hard costs run 10% over budget $34,901
Finished value comes in 5% low $37,940

A cost overrun hurts more than a delay here, because a 10% miss on hard costs is $28,500 of your own cash, not the lender’s. Build a contingency into the budget before you sign the contract, not after the slab is poured.

Stress test of net profit on a Florida ground up construction spec build

Florida Factors That Change a Build

  • Wind and the building code. The Florida Building Code defines a wind-borne debris region, and inside it every exterior opening needs impact-rated glazing or approved shutters. The boundary depends on the design wind speed and the distance from the coast, so it varies by county and even by parcel. Impact windows and strapping are a budget line, not an upgrade. They also affect what the house costs to insure later.
  • Insurance during and after. Builder’s risk covers the project while it is going up, and state law ties opening protection to windstorm loss mitigation. Your buyer or your rental insurer prices the finished house, and roof shape, elevation and wind mitigation features all move that number.
  • Hurricane season. It runs from June 1 to November 30. Crews, inspections and material deliveries all slow down around a storm, so build a buffer into the schedule and the loan term.
  • Impact fees. Many Florida counties charge impact fees at permitting. They can run into five figures on a single-family home and are due long before your first draw.
  • Flood elevation. In a Special Flood Hazard Area, the required finished floor elevation can change the foundation design and add stem wall or fill costs.
  • Permit timelines. They vary widely by jurisdiction. Ask the building department for current review times before you commit to a schedule.

5 Common Mistakes on a First Ground-Up Build

  • Budgeting the lot like a flip down payment. Lenders size on total project cost, so the lot is only one part of the equity you need.
  • Forgetting that draws reimburse. You pay first. Projects stall more often from thin working capital than from a bad budget.
  • Skipping lien paperwork. One unreleased sub can cloud title at exactly the wrong moment, when your buyer is ready to close.
  • Underwriting the sale from list prices. Use closed comps of comparable new construction.
  • Leaving no contingency. A 10% overrun on hard costs is normal enough that it belongs in the budget from day one.

Ground Up Construction Financing FAQ

What is ground up construction financing?

Ground up construction financing is short-term, interest-only financing for building a new structure on vacant land. The lender funds the lot and the construction budget through a draw schedule tied to milestones, then you repay by selling the finished home or refinancing it.

How much do you have to put down on a construction loan?

Most private construction lenders fund 75% to 90% of total project cost, so plan on 10% to 25% of the project in cash, plus closing costs. Your land equity usually counts toward that contribution.

How does a construction draw schedule work?

The lender releases money in stages as milestones finish, usually foundation, framing, dry-in, rough-in, drywall, finishes and completion. Each draw needs a request, an inspection and often lien releases before the funds are released.

Can a first-time developer get a ground up construction loan?

Yes, with the right team. Many construction lenders will work with a first-time ground-up developer who hires an experienced, licensed general contractor, usually at lower leverage. A strong builder, a complete budget and a permitted lot matter more than your own track record. We require at least one ground-up project completed in the last 3 years, sold or refinanced. Work as a licensed GC on another’s build counts as half a project. Fix-and-flips and rentals don’t count.

Do construction loans cover the land?

Yes, most do. The lender typically funds a portion of the lot at closing and the rest of the budget through draws. If you already own the lot, its appraised value usually counts as part of your equity.

What is an interest reserve?

It is loan money set aside to pay interest during the build, when the property produces no income. It keeps you from funding payments out of pocket, but it raises the loan amount and the total interest you pay.

How long does a ground-up construction loan last?

Typically 12 to 24 months, interest only. Build the term around your schedule to the certificate of occupancy plus the time your sale or refinance needs to close.

What happens if my build runs over budget?

You usually fund the overrun. Lenders size the loan at closing against the approved budget, and increasing it mid-build means re-underwriting, if it is possible at all. A contingency line in the original budget is the cheaper answer.

Can a subcontractor put a lien on my property in Florida?

Yes. Under Chapter 713 of the Florida Statutes, a subcontractor or supplier with no direct contract with you can still lien your property. They serve a Notice to Owner, generally within 45 days of first supplying labor or materials. Collect lien releases with every payment.

Should I sell the finished house or keep it as a rental?

Compare the net sale proceeds against what a DSCR refinance would return and what the rent would cover. Decide before you build, because the exit shapes the finishes, the timeline and the loan term you need.

Who finances ground up construction projects for developers?

Private and portfolio lenders do most of this lending, along with some community banks and credit unions. A private construction lender usually moves faster and accepts less experience than a bank, at a higher rate. Banks price lower. They also want more equity, a longer approval and often a borrowing relationship.

Can you get a construction loan with no money down?

Almost never on a ground-up build. Lenders size the loan against total project cost, so they expect 10% to 25% of the project from you. The closest thing to no money down is owning the lot already, since its appraised value usually counts toward your contribution.

What are the biggest challenges in financing a ground-up project?

Three come up repeatedly. The first is the equity gap between what the loan funds and what the project costs. The second is working capital, because draws arrive after the work is done. The third is schedule risk from permits, inspections and weather. A build-ready lot and a contingency in the budget solve most of the rest.

Is ground-up construction better than flipping?

They are different risks. A flip has a standing house and a shorter timeline. A build gives you a new home with no deferred maintenance, and often a better margin. You pay for that with a longer schedule and more things that can go wrong.

How Requity finances ground-up construction

We provide ground up construction financing for residential builds in Florida, and in every state except California, Alaska, Hawaii, North Dakota and South Dakota. We also make the bridge, fix and flip and DSCR loans that sit on either side of a build.

  • Leverage: [VERIFY: maximum LTC and LTARV on the construction program]
  • Loan size and term: [VERIFY: construction loan size range and term options]
  • Rate and fees: [VERIFY: construction starting rate, origination, extension options]
  • Draws: funded against the approved budget as milestones are completed and inspected. [VERIFY: draw turnaround time]
  • Exit: we can line up the DSCR loan that refinances the finished house, so the takeout is planned before you break ground.

Our new construction loans page carries the current program terms.

What to send us for a quote

  • The lot address, purchase price or what you paid, and whether it is permitted
  • Your plans and the itemized construction budget
  • Your builder’s license, insurance and recent projects
  • Your construction schedule and target completion date
  • Comparable sales or rents supporting the finished value
  • Your experience, and the entity that will hold title

You do not need every item to start. Send what you have and we will tell you how the project looks.

Thinking About Breaking Ground in Florida?

The seven questions above decide a build before the first truck arrives. You need a build-ready lot, a complete budget and enough cash for the gaps. You also need a builder who qualifies, lien paperwork from day one, and a financed exit.

Send us the lot and the budget and we will size the loan with you, or call 813.338.1000.

Submit your construction project →

This article is general information as of November 2026 and is not financial, legal or tax advice. Lien law, permitting and code requirements vary by county and change over time, so confirm them with your attorney, your title company and the local building department. The example is illustrative, and the lender terms shown are market-typical rather than a Requity quote. Requity Lending makes business-purpose loans secured by non-owner-occupied investment property. Rates, terms, fees and leverage are set deal by deal and subject to underwriting. A term sheet is not a commitment to lend.